More images are on the New Platform page.
Some of the Project History
The Government has given the approval for the HVCS project. Volker Rail Story JV and Network Rail have started work on the survey work for the project. This is expected to run between April and October 2021.
A project update was provided by the two companies at the end of July 2021. The July 2021 presentation and handout are available here:-
The scheme is estimated at £137million and will provide:-
- an additional track through D&T station, this requires a second platform and bridge between the two platforms to allow passengers to board trains on the Hope Valley line to and from Sheffield
- extending the platform from 115m to 153m
- an extension to the single track which links the Hope Valley line with the Midland Mainline to the west of the D&T station which is used mainly by freight services
- a Bamford Loop which is a place to halt freight trains to allow passenger trains to overtake. This is east of Bamford station
- a new footbridge to the west of Hathersage station to replace an existing crossing for walkers
The main benefits of the scheme should be :-
- increase the number paths for fast trains from 2 to 3 per hour
- to allow a regular hourly stopping service
- to allow for 3 freight trains every two hours as at present
- greater number of seats thus reducing the over crowding on the trains
- allow trains of up to 6 cars to stop at Dore and Totley
- accommodate longer freight trains
- improve reliability on the route.
Here is a project overview:-
Latest Position
A public Inquiry was held in 2016.
The inspector produced the Public Inquiry report and sent it to the Department for Transport(DfT) in November 2016. In Feb 2018 the DfT announced that they agreed with the inspectors report and provided approval for the scheme to progress.
Work has started on the project and the current timetable for the scheme is as follows:-
- Survey Work - April to October 2021
- Site Establishment - Autumn/ Winter 2021
- Construction Works begins - early 2022
- Project Complete - Summer 2023 with possible overrun into 2024
Network Rail Order Inspectors Report and DfT Order Decision Letter
Network Rail Order Inspectors Report
Network Rail Order Decision Letter
Recent announcement and Press Coverage
Government announcement
Railway Technology
Yorkshire Post
Rail Freight
|