Outline Plan as at November 2016
- Phase 1 London Euston to North Of Birmingham
- Phase 2a Fradley to Crewe
- Hybrid Bill development 2016-2017
- Hybrid Bill Phase 2017-2019
- Finalising Design and Construction Phase 2019-2025
- Commissioning and Testing 2025-2027
- Operational phase 2027 onwards
- Phase 2b Crewe to Manchester and West Midlands to Leeds
- Strategic Outline Business Case and proposed route 2016.
- Response to consultation, refined strategic Outline Business Case 2017
- Decision on the full route following consultation in summer 2017
- Hybrid Bill Phase 2019-2022
- Finalising Design and Construction Phase 2022-2032
- Commissioning and Testing 2032-2033
- Operational phase 2033 onwards
|